Construction Projects

March 31, 2026

PROJECTS UNDER CONSTRUCTION

Swimming Pool Rehabilitation

Project includes rehabilitation of the main pool, demolition of the small pool, and improvements to various items within the pool area. Construction is underway with two active contracts:

Premium Pool Solutions

The Board approved Change Order No. 2 to replace swim lanes, which could not be salvaged during plaster removal. The Board approved Pay Request No. 2. Contractor is actively working on plaster removal and replacement and expects to be complete in mid-April.

Waterline Rehabilitation — Phase Two

Project includes replacement of aging waterline infrastructure within Plantation, Section One, with an additional location along Mayweather Lane between Plantation Drive and Morton League Road. Contractor: SKE Construction, LLC. Contractor has submitted all closeout documentation. Engineer has provided a Certificate of Completion to the MUD attorney. Si Environmental is addressing minor concrete items prior to Engineer recommending close out and approval of final pay estimate.

Board Approved Change Order No. 5 which reduced the contract by $52,105.00 for quantity adjustments. The Board approved Pay Request No. 6 for $6,318.00.

Club Facilities — Tennis Court Electrical & Lighting Improvements

Project includes electrical and lighting improvements to serve the tennis courts at Club facilities. Contractor: McDonald Municipal & Industrial System is currently operational under manual operation. The Board approved Change Order No. 2 for $5,000.00 for installation of a surge protector to provide additional protection on the installed system.

WWTP Belt Press Replacement

Project includes replacement of the belt press and corresponding electrical components at the Wastewater Treatment Plant.

  • Notice to Proceed issued March 23, 2026.
  • Contract duration: 400 calendar days. Contractor-submitted project schedule:
    • Mobilization: November 2026
    • Demo existing belt press: December 2026
    • Install new press and controls: January 2027
    • Start-up and testing: February 2027

Electrical Improvements at District Lift Stations

Project includes electrical improvements at District lift stations. Contractor is working through minor insurance comments prior to issuance of Notice to Proceed.

Projects Under Design

Water Distribution and Wastewater Utility Extension along Brandt Road

Project includes installation of a waterline and sanitary sewer line along Brandt Road. Funding: Operating Funds. Plans have been approved by all agencies. Advertising of the project is contingent on execution of the PILOT agreement with Esteem AI Ventures for out-of-District services. Engineer will request authorization to advertise pending execution of that agreement.

Sanitary Sewer and Drainage Improvements to Serve The Club at Pecan Grove

Project includes rehabilitation of drainage and sanitary sewer lines within the Club facility. Funding: Bond Issue No. 19.

  • Project Schedule:
    • Plans Complete: April 2026
    • Open Bids: June 2026
    • Notice to Proceed: September 2026
    • Project Complete: December 2026

Engineer is working on final construction plans per the above schedule.

Reclaimed Water System and Conveyance Line

Project includes design and installation of a Phase 1 water effluent reuse system, including discharge piping to connect to the pond at the intersection of FM 359 and Plantation Drive. Funding: Bond Issue No. 19.

  • Project Schedule:
    • Agency Approval: April 2026
    • Open Bids: June 2026
    • Notice to Proceed: September 2026
    • Project Complete: April 2027

Electrical engineer is finalizing plan updates prior to obtaining plan signatures.

South Pump Station Headwall Improvements and Redundant Gate Closures

Project includes design and modification of the concrete headwall at the south pump station and installation of sluice gates on the upstream end of the box culvert connection through the levee. Funding: Bond Issue No. 19. Plans have been approved by all agencies. The Board authorized the Engineer to advertise the project for bidding. Bids are expected to be presented to the Board in June 2026.

Bond Issue No. 19

Engineer is finalizing the bond application report based on comments from consultants. Bond issue expected to be submitted to TCEQ in April 2026.

Other Engineering Items

Detention Basin Aerator — Holes 2 & 3, Plantation Drive

CDC has provided an updated proposal for installation of an Otterbine aerator at the detention basin near Holes 2 & 3 off Plantation Drive. Installation proposal: $12,885. The Board approved the CDC proposal for aerator installation.

Slope Paving Repairs — Main Channel and Pecan Lakes Pump Station

Inspections have identified small voids under existing slope paving at the Main Channel and Pecan Lakes Pump Station. CDC has provided quotes for flowable fill and concrete patching:

  • Main Channel: $2,500
  • Pecan Lakes Pump Station: $2,500.
  • Plus additional consideration for allowances of flowable fill.

The Board approved the CDC proposal for flowable fill and concrete patching.

Fence Encroachment — 2119 Summerland Drive

A resident at 2119 Summerland Drive requested formal consideration for a fence encroachment on District property. The encroachment was previously allowed by a previous golf course owner due to existing drainage features. The matter was tabled at the February 2026 meeting. At the March 31, 2026 meeting, the Board considered and denied the encroachment request.

MS4 Annual Report — TPDES Permit TXR040225

The Board approved the Annual MS4 Storm Water Report for submittal to TCEQ.


Engineering Updates – Archive