Construction Projects

October 27, 2026

ENGINEER’S REPORT

PROJECTS UNDER CONSTRUCTION

WWTP Belt Press Replacement

Project includes replacement of the belt press and corresponding electrical components at the Wastewater Treatment Plant. Contractor remains on schedule with mobilization scheduled for November 2026. Demolition of the existing belt press scheduled for December 2026. Installation of the new belt press and controls scheduled for January 2027. Startup and testing scheduled for February 2027.

Electrical Improvements at District Lift Stations

Project includes installation of natural gas generators and automatic transfer switches (ATS) at Lift Stations No. 2, 4, and 9. Generator and ATS equipment are scheduled to arrive during the first week of December 2026. Project completion is anticipated in early 2027. Engineer is coordinating with CenterPoint Gas regarding extension of natural gas service to the generator sites. The Board approved Pay Request No. 2 in the amount of $22,203.00.

South Pump Station Headwall Improvements and Redundant Gate Closures

Project includes modification of the concrete headwall at the south pump station and installation of sluice gates on the upstream end of the box culvert connection through the levee. Delivery of the sluice gates is anticipated in March 2027.

Wren Meadow Storm Sewer and Pavement Repair

Project includes repair of a failed storm sewer lead and associated pavement displacement at 2307 Wren Meadow Lane. Notice to Proceed was issued effective October 5, 2026. Contractor is working through permitting requirements with Fort Bend County prior to beginning construction.

Club Facilities — Tennis Court Electrical & Lighting Improvements (Warranty Work)

The lighting manufacturer has agreed to replace all fixture lights. Scheduling for replacement work is currently being finalized.

PROJECTS UNDER DESIGN & BIDDING

Reclaimed Water System and Conveyance Line

Project includes design and installation of a Phase 1 reclaimed-water system and conveyance line to the pond near FM 359 and Plantation Drive. Four bids were received with Provident Water Group, LLC was the low bidder at $2,965,065.20. The Engineer recommended award of the contract to Provident Water Group, LLC. Board awarded the project to Provident.

Water Distribution and Wastewater Utility Extension along Brandt Road

Project includes installation of a waterline and sanitary sewer line along Brandt Road. Construction contracts are currently being executed.

Sanitary Sewer and Drainage Improvements to Serve The Club at Pecan Grove

Project includes rehabilitation of drainage and sanitary sewer lines within the Club facility. Construction contracts are currently being executed.

OTHER ENGINEERING ITEMS

Levee Damage along Mason Road

Engineer determined the safest method to repair contractor-caused levee damage is excavation and reconstruction of the affected area. Estimated repair and oversight costs total approximately $26,090 and reimbursement is being sought from the contractor.

Sealing of Flood Wall Along Jones Creek

Odyssey recommends sealing seven joints in the floodwall along Jones Creek. LiquaTech submitted the recommended proposal in the amount of $10,251. Board awarded the project to LiquaTech

2026-2027 Capital Improvement Program

Board authorized Engineer to begin professional services for the following projects in connection with the District’s 2026-2027 Budget and Capital Improvement Plan

  • North Storm Water Pump Station redundant closures and flap gate replacements
  • Drainage improvements north of Belin Park
  • Surface Water Treatment Plant raw water quality monitoring improvements
  • Generator improvements at Lift Station 6, 7 and 8.


Engineering Updates – Archive