October 27, 2026
ENGINEER’S REPORT
PROJECTS UNDER CONSTRUCTION
WWTP Belt Press Replacement
Project includes replacement of the belt press and corresponding electrical components at the Wastewater Treatment Plant. Contractor remains on schedule with mobilization scheduled for November 2026. Demolition of the existing belt press scheduled for December 2026. Installation of the new belt press and controls scheduled for January 2027. Startup and testing scheduled for February 2027.
Electrical Improvements at District Lift Stations
Project includes installation of natural gas generators and automatic transfer switches (ATS) at Lift Stations No. 2, 4, and 9. Generator and ATS equipment are scheduled to arrive during the first week of December 2026. Project completion is anticipated in early 2027. Engineer is coordinating with CenterPoint Gas regarding extension of natural gas service to the generator sites. The Board approved Pay Request No. 2 in the amount of $22,203.00.
South Pump Station Headwall Improvements and Redundant Gate Closures
Project includes modification of the concrete headwall at the south pump station and installation of sluice gates on the upstream end of the box culvert connection through the levee. Delivery of the sluice gates is anticipated in March 2027.
Wren Meadow Storm Sewer and Pavement Repair
Project includes repair of a failed storm sewer lead and associated pavement displacement at 2307 Wren Meadow Lane. Notice to Proceed was issued effective October 5, 2026. Contractor is working through permitting requirements with Fort Bend County prior to beginning construction.
Club Facilities — Tennis Court Electrical & Lighting Improvements (Warranty Work)
The lighting manufacturer has agreed to replace all fixture lights. Scheduling for replacement work is currently being finalized.
PROJECTS UNDER DESIGN & BIDDING
Reclaimed Water System and Conveyance Line
Project includes design and installation of a Phase 1 reclaimed-water system and conveyance line to the pond near FM 359 and Plantation Drive. Four bids were received with Provident Water Group, LLC was the low bidder at $2,965,065.20. The Engineer recommended award of the contract to Provident Water Group, LLC. Board awarded the project to Provident.
Water Distribution and Wastewater Utility Extension along Brandt Road
Project includes installation of a waterline and sanitary sewer line along Brandt Road. Construction contracts are currently being executed.
Sanitary Sewer and Drainage Improvements to Serve The Club at Pecan Grove
Project includes rehabilitation of drainage and sanitary sewer lines within the Club facility. Construction contracts are currently being executed.
OTHER ENGINEERING ITEMS
Levee Damage along Mason Road
Engineer determined the safest method to repair contractor-caused levee damage is excavation and reconstruction of the affected area. Estimated repair and oversight costs total approximately $26,090 and reimbursement is being sought from the contractor.
Sealing of Flood Wall Along Jones Creek
Odyssey recommends sealing seven joints in the floodwall along Jones Creek. LiquaTech submitted the recommended proposal in the amount of $10,251. Board awarded the project to LiquaTech
2026-2027 Capital Improvement Program
Board authorized Engineer to begin professional services for the following projects in connection with the District’s 2026-2027 Budget and Capital Improvement Plan
- North Storm Water Pump Station redundant closures and flap gate replacements
- Drainage improvements north of Belin Park
- Surface Water Treatment Plant raw water quality monitoring improvements
- Generator improvements at Lift Station 6, 7 and 8.
Engineering Updates – Archive
- Engineering Updates – October 27, 2026
- Engineering Updates – September 22, 2026
- Engineering Updates – August 25, 2026
- Engineering Updates – July 28, 2026
- Engineering Updates – June 30, 2026
- Engineering Updates – May 26, 2026
- Engineering Updates – April 28, 2026
- Engineering Updates – March 31, 2026
- Engineering Updates – February 24, 2026
- Engineering Updates – January 27, 2026
- Engineering Updates – December 16, 2025
- Engineering Updates – November 18, 2025
