Jones Creek Rehabilitation Construction Notification

The Contractor has begun drilling operations associated with repairing the bank of Jones Creek. This activity will be loud at times and we appreciate the patience and understanding of nearby residents.

The Contractor is allowed to work from 7 a.m. until sunset for seven days a week. At this time, the Contractor does expect to work seven days a week in order to achieve the project delivery schedule.

During this time, please remember this is a construction site and stay safe! Please keep out of the construction area and instruct children not to play in or around the construction site.

If you have any questions about the work, please contact the District office at 281-238-5000.

Jones Creek Rehabilitation Construction Notification

As you have seen, the Contractor for the construction project, Jones Creek Rehabilitation, has started with preliminary measures to assist construction access to the project. This work includes construction of access roads, temporary irrigation and the construction of the material staging area located north of the Pecan Lakes subdivision.

On Monday, October 14 the Contractor will begin the demolition of the existing structures. This activity will be loud at times and we appreciate the patience and understanding the residents that are directly affected by this construction activity.

The Contractor is allowed to work from 7 a.m. until sunset for seven days a week and, at this time, the Contractor does expect to work seven days a week in order to achieve the project delivery schedule.

During this time, please remember this is a construction site and stay safe! Please keep out of the construction area and instruct children not to play in or around the construction site.

If you have any questions about the work, please contact the District office at 281-238-5000.

Construction Notification

Dear Pecan Grove Resident,

As part of our ongoing efforts to maintain the levee facilities in the community, Pecan Grove Municipal Utility District has awarded the contract for the Jones Creek Rehabilitation project to Texas Wall & Landscape (TWL). This project will repair the slope failures along Jones Creek behind the Pecan Lakes subdivision that were caused by Hurricane Harvey. The construction project involves removing the existing sheet piling and constructing a soldier pile wall with gabion basket slope protection. The gabion basket system is the preferred system for slope stabilization by the U.S. Army Corps of Engineers due to their flexibility during the life of the project as well as their ability to allow saturated soils to more freely drain without impacting the structural stability of the overall system. The gabion system has successfully been used in similar areas along the Brazos River and Jones Creek. Please visit the Districts’ website for more information.

TWL will begin construction as early as the first week of October 2019. The construction project is expected to take 220 days, depending on weather and the conditions of the Brazos River. Due to the expedited construction schedule, TWL will be working seven (7) days a week from 7 a.m. until sunset. We are receiving federal funding for a significant portion of the design and construction and expedited construction is necessary to meet the federal funding requirements. We apologize in advance for the fact that the construction will be loud at times.

TWL will access the site from the north via F.M. 359 and from the east via a haul road from FM359, just north of the Pecan Grove Baptist Church. Please be mindful of the construction traffic in these areas.

During this time please remember this is a construction site and stay safe! Please keep out of the construction area and instruct children not to play in or around the construction site.

If you have any questions about the work, please contact the District office at 281-238-5000.

PGMUD July 2019 Project Highlights

Please find below a partial list of projects in various stages of completion now underway in Pecan Grove MUD. This information is being provided so that you can stay up to date on these projects which are discussed at every meeting of the board of directors. To view the status of a particular project, please visit the construction projects page. If you have a question or comment about any topic, please call EDP, the district’s operator, at (281) 238-5000. And as always, if you would like to address the district’s engineer or the board, please join us at the next regular meeting August 27 at the Pecan Grove Baptist Church starting at 5:30 p.m.

PROJECT HIGHLIGHTS 

  • Motor Control Center (MCC) Update for Water Plant No. 2
  • Bent Creek Court Drainage Improvements
  • Improvements to Raw Water Tanks at Surface Water Treatment Plant
  • Lift Station No. 4 Rehabilitation
  • Levee Drainage Improvements Adjacent to Harvest Green
  • Mason Road Levee Improvements
  • Main Channel Rehabilitation
  • Jones Creek Slope Rehabilitation
  • Culvert Rehabilitation at Mayweather
  • Drainage Improvements to Serve Victoria Garden Drive