Highlights of Pecan Grove MUD Meeting – April 29, 2025

The regular monthly meeting of the Pecan Grove Municipal Utility District was held at the Pecan Grove MUD Administration/Community Building at noon on April 29, 2025. The next regular meeting is scheduled for Tuesday, May 27, 2025, in the PGMUD building at noon.

PGVFD Report — April 2025

Total Calls for March: 127
Total Incidents for 2025: 507

Parks and Facilities Report

Key card readers have been installed and are necessary at the pool, fitness center, and tennis courts. The cards can be obtained at the PGMUD office. See Engineers Report for news on project plans for these areas. The missing water fountains at Pecan Grove Park have been replaced. Parts are on order to repair the air conditioning at the Administration/Community building. Trees damaged last year in Hurricane Beryl have been replaced. New landscaping at Windmill Park has been completed.

The Club at Pecan Grove

Chuck Odom reported on projects and changes at The Club at Pecan Grove. Work is continuing on the repairs to the golf course irrigation system. The work on the greens should begin in May. The golf course renovation will begin with the rebuilding of the Grove and Plantation courses this summer. Water fountains will be added to the restrooms on the golf course. There were 715 rounds of golf played in March.

Marketing to the general public has started. There will be repairs to the walls around the front lake. The club membership dues’ structure has been simplified.

In the club building, renovation of the dining area is basically complete with service downstairs now standard and brunches began on Easter Sunday. The club building will be power washed and repainted. The front doors will be refinished.

Remember that key-card access to the pool, workout room, and tennis courts is now required. Cards can be purchased at the MUD office.

Operator Report — Si Environmental, LLC

Water Accountability
  • Percent Accountability: 89.1%

  • Surface Water Treatment Plant (SWTP) Capacity: 91.5%

  • Total Metered Water: 40,253,000

  • Amount Produced: SW 41.012M | Ground 6.131M (47,143,000)

  • Amount Unaccounted for: 4,907,000

  • Amount Used for Maintenance, Est.: 322,000

  • Amount Used Due to Known Leaks, Est.: 4,092,000

  • Adjusted Accountability: 98.9%

March 2025 testing showed that the drinking water and wastewater systems met the state and federal compliance standards for disinfection, and there were no permit excursions for the month.

The repairs of the SWTP raw pumps #1 and #2 plus the #1 motor, are complete along with the replacement of the #2 sludge pump. Repair of the levee sluice valve on the emergency interconnect with Harvest Green is complete. Also completed were the replacement of the Colorimetric Chlorine Analyzer at the SWTP, the fabrication and installation of shelving at the WWTP, and the repair of lift pump at Lift Station #1. At Lift Station #10, the #1 pump will be replaced. At the SWTP, we need a replacement chain for the sedimentation basin collectors, and the rental of a mobile crane will be needed to inspect the raw mixing unit.

At the SWTP, the replacement of the skid C pump and motor are now in-house and are pending installation. New surge protection for Water Plant #2 is in process, as is the replacement of the check valves #3 and #4. The repair at Lift Station #9 on the #1 motor is in process, and replacement of the Raw Check Valve #3 at the SWTP is in process.

Fire hydrant flushing was completed in April, and the painting of all 412 hydrants and the blue dots that need replacement are in process.

The repair of the altitude valve at the elevated storage tank was determined to be inadequate, so a new repair and key component replacement were authorized. Si Enviro and the contractor are working to replace the Solar Bee tank mixer at the elevated storage tank.

At the SWTP, the 10″ Raw Water Check Valve was authorized to be replaced, as was the Colorimetric Chlorine Analyzer. At the WWTP, Si Enviro was authorized to fabricate and install 22″ shelving to provide additional storage space.

The upgrade to the camera system has been completed, except for the WWTP, which is in process.

SI Enviro requested authorization to buy a 4″ diesel trailer-mounted pump set. The unit will be used to maintain the water level in Bullhead Bayou during low water situations.

On March 11, 2025, the TECQ performed a general compliance inspection at the WWTP. There were no violations noted at the time of the inspection.

Old water meters continue to be replaced, with 16 replaced this month for a total of 1,721 replaced to date since January 2023.

Residents are urged to call Si Enviro first if there is an outside water leak: (832) 490-1601.

Click here to view Projects Under Construction and Design.

Highlights of Pecan Grove MUD Meeting – March 25, 2025

The regular monthly meeting of the Pecan Grove Municipal Utility District was held at the Pecan Grove MUD Administration/Community Building at noon on March 25, 2025. The next regular meeting is scheduled for Tuesday, April 29, 2025, in the PGMUD building at noon.

Precinct One Constable Report


Pecan Grove Volunteer Fire Department

Parks and Facilities Report

Key card readers have been installed and are necessary at the pool, fitness center, and tennis courts. The cards can be obtained at the PGMUD office. See Engineers Report for news on project plans for these areas. The missing water fountain at Pecan Grove is being replaced. New mulch was spread at Memorial Park. New Vitek bushes were planted along Mason Road, where the ligustrum used to be. Parts are on order to repair the air conditioning at the Administration/Community building. Parks and facilities signage at our recreational facilities. New landscaping around the Fitness Center has been completed.

The Club at Pecan Grove

Chuck Odom reported on projects and changes at The Club at Pecan Grove. Work is continuing on the repairs to the golf course irrigation system. There will be repairs to the walls around the front lake. The golf course renovation will begin with the rebuilding of the Grove and Plantation nines this summer. Marketing to the general public is starting in April.

In the club building, renovation of the dining area is basically complete with service downstairs starting the first week in April. They will be adding brunches to their dining options. The front doors to the club are going to be replaced.

Operator Report — Si Environmental, LLC

Water Accountability

  • Percent Accountability: 95.5%
  • Surface Water Treatment Plant (SWTP) Capacity: 25.8%
  • Total Metered Water: 41,524,000
  • Amount Produced: SW 41.012M | Ground 6.131M
  • Total: 43,463,000
  • Amount Unaccounted for: 1,939,000
  • Amount Used for Maintenance, Est.: 549,000
  • Amount Used Due to Known Leaks, Est.: 1,409,000
  • Adjusted Accountability: 100.0%

February 2025 testing showed that the drinking water and wastewater systems met the state and federal compliance standards for disinfection, and there were no permit excursions for the month.

The repairs of the SWTP raw pumps #1 and #2 plus the #1 motor are complete, along with the replacement of the #2 sludge pump. Repair of the levee sluice valve on the emergency interconnect with Harvest Green is complete.

The replacement of the skid C pump and motor is in process. New surge protection for Water Plant #2 is in process, as is the replacement of the check valves #3 and #4. The repair at Lift Station #9 on the #1 motor is in process.

The repairs to the district’s fire hydrants are complete. The painting of all 412 hydrants and the blue dots that need replacement are in process.

The repair of the altitude valve at the elevated storage tank is complete. New key card access to some of the district’s facilities, plus new additional cameras, are complete.

Si Enviro and the district engineer are investigating how best to repair or replace the Solar Bee tank mixer at the elevated storage tank. Recommended preventative maintenance on the jet machine is complete.

At the SWTP, the 10″ Raw Water Check Valve was authorized to be replaced, as was the Colorimetric Chlorine Analyzer. At the WWTP, Si Enviro was authorized to fabricate and install 22″ shelving to provide additional storage space.

The annual fire hydrant flushing will begin about April 21st.

Old water meters continue to be replaced, with 9 replaced in March for a total of 1,709 replaced to date.

Residents are urged to call Si Enviro first if there is an outside water leak: (832) 490-1601.

Click here to view Projects Under Construction and Design.

Highlights of Pecan Grove MUD Meeting – February 25, 2025

The regular monthly meeting of the Pecan Grove Municipal Utility District was held at the Pecan Grove MUD Administration Building at 5:30 p.m. on February 25, 2025. The next regular meeting is scheduled for Tuesday, March 25, 2025, in the PGMUD Community/Administration building at noon.


Precinct One Constable Report


PGVFD Report — January 2025


Parks and Facilities Report

Key card readers have been installed at the pool, fitness center, and tennis courts. Use of these cards is planned to begin March 10. See Engineers Report for news on project plans for these areas. Terry Landscaping has started site work around the fitness center.


The Club at Pecan Grove

Ralph Shelbourne reported on projects and changes at The Club at Pecan Grove. This summer, The Grove and Plantation golf courses will be rebuilt — one nine at a time. Work has started on repairs to the irrigation system.

In the club building, renovation of the dining area continues. In the temporary restaurant upstairs, the club will be adding some brunches. Marketing to the public is planned to begin in March. Repair work to the wall around the lake in front of the building is being planned. The front doors to the club are going to be replaced.


Operator Report — Si Environmental, LLC

Water Accountability

  • Percent Accountability: 90.7%
  • Surface Water Treatment Plant (SWTP) Capacity: 83.2%
  • Total Metered Water: 42,775,000
  • Amount Produced:
    • SW: 37.296M
    • Ground: 12.304M
    • Total: 47,143,000
  • Amount Unaccounted for: 6,570,000
  • Amount Used for Maintenance, Est.: 1,940,000
  • Amount Used Due to Known Leaks, Est.: 1,290,000
  • Adjusted Accountability: 97.6%

January 2025 testing showed that the drinking water and wastewater systems met the state and federal compliance standards for disinfection, and there were no permit excursions for the month.

The repairs of the SWTP raw pumps #1 and #2 plus the #1 motor are in process. Replacement of the #2 sludge pump is in process. The replacement of the skid C pump and motor is in process. The replacement of the sludge pump #2 is in process.

New surge protection for Water Plant #2 is in process, as is the replacement of the check valves #3 and #4. The repair at Lift Station #9 on the #1 motor is in process. Repair of the levee sluice valve on the emergency interconnect with Harvest Green is in process.

The repairs to the district’s fire hydrants are in process, as is the painting of all 412 hydrants. The blue dots that need replacement are being addressed.

The repair of the altitude valve at the elevated storage tank is in process.

New key card access to some of the district’s facilities, plus new cameras, is complete.

Si Enviro was authorized to replace the Solar Bee tank mixer at the elevated storage tank. Recommended preventative maintenance on the jet machine was authorized.

The annual performance testing on the district’s water wells was completed with no problems noted.

Old water meters continue to be replaced, with 27 replaced in February for a total of 1,696 replaced to date.

Residents are urged to call Si Enviro first if there is an outside water leak.


TAXES

Tax collections for fiscal 2025 have reached 73.56% as of 1/31/2025.


Click here to view Projects Under Construction and Design.

Highlights of Pecan Grove MUD Meeting – January 30, 2025

The regular monthly meeting of the Pecan Grove Municipal Utility District was held at the Pecan Grove Administration Building at noon on January 30, 2025. The next regular meeting is scheduled for Tuesday, February 25, 2025, in the PGMUD Community/Administration building at 5:30 p.m.

Fort Bend County Constable Precinct 1
Monthly Contract Report for January 2025

 

PGVFD Report – January 2025

Parks and Facilities Report

  • New cameras have been installed at Pecan Grove Park and at the pool and workout facilities at the club.
  • New access locks with key fobs are being installed at the tennis and pool gates at the club.
  • The work on the fences for the tennis courts has been completed.
  • A contract for maintaining the workout building was signed.
  • The problems with HVAC at the Administration/Community building are being addressed.

The Club at Pecan Grove

  • Chuck Odom reported that repairs are progressing on the golf course irrigation system.
  • Plans for 2025 include a budget of $1.75 million to rebuild 18 holes.
  • Overall, the whole course is improving even before the major rebuild project begins.
  • The restroom buildings have been repaired and painted.
  • In the Clubhouse, renovations are in process that includes new floor coverings and painting.

Operator Report – Si Environmental, LLC

Water Accountability

  • December 2024 testing showed that the drinking water and wastewater systems met the state and federal compliance standards for disinfection, and there were no permit excursions for the month.
  • Repairs:
    • Repairs of the SWTP raw pumps #1 and #2 plus the #1 motor are in process.
    • Replacement of the #2 sludge pump was authorized at the meeting.
    • Replacement of the skid C pump and motor is complete.
    • The annual contract for Hach Services for the SWTP will be renewed.
  • New Projects:
    • New surge protection for Water Plant #2 is in process.
    • Replacement of the check valves #3 and #4 was approved.
    • Repair at Lift Station #9 on the #1 motor is in process.
    • Si Enviro was authorized to repair the levee sluice valve on the emergency interconnect with Harvest Green.
  • Fire Hydrants:
    • Repairs to the district’s fire hydrants are in process.
    • Painting of all 412 hydrants is in process.
    • Blue dots that need replacement are being addressed.
  • Elevated Storage Tank:
    • Repair of the altitude valve at the elevated storage tank is in process.
  • Security:
    • New key card access to some of the district’s facilities plus new cameras are in process.
  • Annual Shutdown:
    • The annual shutdown of the SWTP for scheduled maintenance will begin February 7, 2025.
    • At that time, the annual exchange of the Activated Charcoal will be performed, and the cleaning of the raw water intake, sedimentation basin, and the clear well will occur.
  • Meter Replacement:
    • The program to replace high-usage residence meters continues in the district, with 1,669 meters replaced since January 2023.
  • Residents are urged to call Si Enviro first if there is an outside water leak.

TAXES

  • Tax collections for fiscal 2025 have reached just over 12.7% as of 12/31/2024.

Click here to view Projects Under Construction and Design.