Engineer’s Report
Projects Under Construction
Generators for Water Plant No. 1 and Water Well No. 5
Project includes installing natural gas generators for the water plant located on Pitts Road and the remote water well located near Austin Elementary. Engineer reported that Centerpoint has installed gas meter for water plant no. 1 and is still pending installation at water well no. 5. Start up on water plant no. 1 was held and there are minor punchlist items for the Contractor to address.
Levee Property Acquisition
Engineer reported the Notice to Proceed was issued to Contractor, Greenscape & Associates, on November 14, 2022. Engineer reported that the project is substantially complete, pending submittal of final paperwork from Contractor.
Sanitary Sewer Rehabilitation
Project consists of rehabilitation of existing sanitary sewer lines within the District. Contract was previously awarded to King Solutions Services, LLC. Field work on the project is complete. Close out pending submittal of final paperwork from Contractor.
Northwest Pecan Grove Park Ramp
Project includes construction of a ramp and trail to facilitate access to the walking trail on top of the levee as it passes through Pecan Grove Park on Pitts Road. Field work on the project is complete. Close out pending submittal of final paperwork from Contractor.
Waterline Rehabilitation – Phase 1
Project includes design and construction replacement waterline along Morton League Road. Paid for out of Bond Issue No. 18. Notice to Proceed was issued on April 26, 2023 and as of the meeting the Contractor was approximately 50% complete with construction. Odyssey is working with the Contractor to improve project cleanliness and traffic control and is responding to residents’ concerns that have been communicated to the District. Additionally, the Board approved Pay Request No. 1 in the amount of $82,926.00.
Pecan Grove Park Perimeter Walking Trail/Sidewalk
Project includes design and construction of a walking trail around Pecan Grove park. Paid for out of Operating Budget 2023. Notice to Proceed was issued on May 1, 2023 and the Contractor was approximately 75% complete with the project at the time of the meeting. The Board did approve Change Order No. 1in the amount of $3,600 to add additional drainage culverts to promote positive drainage in the area of the walking trail.
Projects Under Design
Facility Arc Flash Study – Phase 1
Project includes analysis of District facilities with control panels to ensure compliance with current electrical standards. Phase 1 includes surface water treatment plant and water plant nos. 1, 2 & 3. Paid for out of Operating Budget 2023. Preliminary engineering is underway and information from Centerpoint has been requested to proceed with the study.
- Preliminary Schedule
- Authorize Phase 1 Study – October 2022
- Study Complete – March 2023
Rehabilitation of Chemical Feed System at Surface Water Plant
Project includes modifications and rehabilitation of the chemical feed system at the surface water plant to increase efficiency and due to components reaching design life. Bids will be opened on May 25, 2023 and presented at the June 2023 meeting.
- Preliminary Schedule
- Design and Plan Production – Complete December 2022 (90 days)
- Solicit Bids and Execute Contracts – Start January 2023 (90 days)
- Anticipated NTP – early 2nd Quarter 2023
- Construction Complete – 3rd Quarter 2023
Storm Sewer Outfall and Levee Penetration Televising
Project includes inspection of all storm sewer outfalls and pipes that penetrate the levee to determine pipe conditions.
Televising report has been received by Engineer and is under review. Recommendations expected to be presented at the June meeting.
Access Road at North Pump Station
Project includes improvements of access road to serve the North Pump Station. Engineer reported that plans fully approved and contracts with ICS are currently being reviewed by the MUD attorney.
- Schedule
- Solicit Bids and Execute Contracts – Start March 2023 (60 days)
- Anticipated NTP –2nd Quarter 2023
- Construction Complete – 3rd Quarter 2023
Internal Drainage and Ponding Study
Project includes detailed flooding analysis incorporating Fort Bend County increase rainfall intensities as well as determining the primary location of ponding inside the levee. Paid for out of Operating Budget 2023. Preliminary engineering is underway.
- Schedule
- Preliminary Report Complete – May 2023
- Agency Review – Complete July 2023 (60 days)
- Finalize Report – August 2023 (30 days)
Old South Drive Culvert and Road Repairs
Project includes removing and replacing a portion of Old South Drive over the culvert connection of Bullhead Bayou. Project will also include grout filling and stabilization of any erosion discovered during road repair. Paid for out of Operating Budget 2023. Engineer reported that plans are in for agency approval. Bids will be received in June 2023.
- Schedule
- Anticipated NTP –late 2nd Quarter 2023
- Construction Complete – 3rd Quarter 2023
South Pump Station Generator
Project includes replacement of existing diesel generator at the South Pump Station. Paid for out of Bond Issue No. 18. Bids will be opened on May 23, 2023 and presented at the June 2023 meeting.
- Schedule
- Advertise Bids and Execute Contracts – May 2023 (90 days)
- Anticipated NTP –3rd Quarter 2023
- Construction Complete – 3rd Quarter 2024
South Pump Station Headwall Modification and Redundant Closure Devices
Project includes modification of headwall structure for the South Stormwater pump station to allow for the design and installation of back up closure devices. Design Paid for out of Bond Issue No. 18. Construction to be funded by a future bond issue. Geotechnical information has been received and final structural design is underway.
- Schedule
- Agency Review completed by mid-April 2023
- Revise Plans and Resubmit for Approval – end of May 2023
- Plans Fully Approved – end of June 2023
North Pump Station Redundant Closure Devices
Project includes design and installation of back up closure devices at the North Pump Station. Design Paid for out of Bond Issue No. 18. Construction to be funded by a future bond issue. Geotechnical information has been received and final structural design is underway.
- Schedule
- Agency Review completed by May 2023
- Revise Plans and Resubmit for Approval – June 2023
- Plans Fully Approved – July 2023
Wastewater Treatment Electrical Improvements & Generator Replacement
Project includes update of the control panel and related electrical system at the wastewater treatment plant as well as replacement of the existing generator. Paid for out of Bond Issue No. 18. Bids will be opened on June 19, 2023 and presented at the June 2023 meeting.
- Schedule
- Advertise Bids and Execute Contracts – May 2023 (90 days)
- Anticipated NTP –3rd Quarter 2023
- Construction Complete – 3rd Quarter 2024
Additional Engineering Items
Contracts for chemical injection stabilization of Pecan Lake flood wall with Eco Soil Stabilizers is currently being executed by Contractor.
Contracts for replacement of grouting of Pecan Lakes flood wall to CFG Industries is currently being executed by Contractor.
Board approved an agreement with Centerpoint Energy in the amount of $5,135 to relocate a power pole and guy wire located in the levee behind 1515 Savannah.
Odyssey prepared and submitted, on behalf of the District, an application to the Texas Water Development Board, for consideration of funds to mitigate the Lead and Copper requirements mandated by the EPA.