Report by the District’s Engineer (Odyssey Engineering Group)
PROJECTS UNDER CONSTRUCTION
Electrical Improvements and Generator at Water Plant No. 2
The District is updating the electrical system including installation of a new generator at water plant no. 2 (located near the elevated storage tank).
Project is complete pending installation of new electrical meter from Centerpoint to the facility. Once that is installed, Contractor will finalize punchlist items and project will be closed out.
Improvements at Water Plant No. 3
The District is modifying the pumps and piping system at water plant no. 3 (located at the end of Willow Bend Dr.).
Project is nearly complete with minor punchlist items to be addressed by the Contractor, WW Payton, prior to final inspection. Contractor worked late into the night during the ice storm to place the water plant into emergency operations, assisting the District in maintaining water pressure during the event.
Automatic Transfer Switch for Water Plant 1 & Water Well 5
Project includes installation of necessary components to allow the connection of a portable generator to provide electricity to the facilities, if the electrical grid is not providing the required electricity.
Project has been awarded to McDonald Electric and material has been ordered. Once the equipment arrives on site, contractor will mobilize to install the required facilities.
Epoxy Repairs on Structural Levee
Project includes re-grouting and applying of epoxy to maintain the structural levee walls in the District.
Project was awarded to CFG Industries and project is expected to commence in Spring 2021.
Bullhead Slough – Phase Two
Project will dredge and rehabilitate the side slopes of the portion of Bullhead Slough between Oyster Creek and Farmer Road.
Contractor has begun construction on the project. Residents are reminded that this is an active heavy construction site. DO NOT enter construction site at any time. Unauthorized access to the construction area places the unauthorized visitor and construction crews at risk.
Main Channel Clean Out – Phase Two and Three
Project includes dredging of the main drainage channel between Pitts Road and Plantation Road and the South Pump Station, located at F.M. 359.
Contractor, Environmental Allies, has mobilized and started the channel clean out.
PROJECTS UNDER DESIGN
Administration Building
Project includes construction of an administration building to serve the District and community at the southern edge of Pecan Grove Park on Pitts Road (adjacent to the PGVFD south station).
Plans have been submitted to local agencies for permit approval. Construction is expected to commence in early 2021, pending agency permits.
Sanitary Sewer Smoke Testing and Televising
District authorized Odyssey and EDP to proceed with the budgeted smoke testing and televising of older sections of sanitary sewer collection system to determine if any structural issues exist in the system.
District authorized Odyssey to received bids for the smoke testing and televising for the following areas of the District:
- Plantation Sections 6, 9, 12 & 22
- Greens Sections 1 & 2
- Rock Fence Dr. and Bittersweet Dr. (Plantation Sections 4 & 5)
- Plantation Place
- Lakeside Dr. (Pecan Lakes, Section 2)
Bids will be opened on March 2, 2021.
Prior to activities, which is expected to begin in Spring 2021, residents will be notified.
Surface Water Plant Driveway Modifications
Due to Fort Bend County’s planned extension of Brandt Road and planned intersection modifications of Brandt Road and Skinner Lane, the District’s driveway to the surface water treatment plant must be modified to accommodate future access. The District will be reimbursed for engineering and construction costs of these modifications. Modifications include relocation of driveway, access gate and related fencing and electrical work to accommodate new entry location.
Construction plans have been submitted for agency review.
OTHER ENGINEERING ITEMS
AT&T Damage to District Facilities
Odyssey continues to work with AT&T regarding the unauthorized access and installation of fiber optic lines in the levee. District will repair the areas damaged with reimbursement from AT&T.