Construction Projects

February 27, 2024

Engineer’s Report

Projects Under Construction

Levee Repairs at 1603 Savannah

Project includes removing a large tree which is dying located at the toe of the existing levee, backfilling and repairing the levee, as necessary, and installation of swing gates to facilitate maintenance.

Project consists of the following scope:

  • Bee Hive Removal & Relocation
  • Tree, Retaining Wall Removal and Levee Reconstruction
  • Gate and Fence Installation

Bee hive has been removed and relocated.  Tree is removed and CDC is working on reestablishing the levee in that location.

Rehabilitation of Chemical Feed System at Surface Water Plant

Project includes modifications and rehabilitation of the chemical feed system at the surface water plant to increase efficiency and due to components reaching design life. Construction continues on site.

Wastewater Treatment Electrical Improvements & Generator Replacement

Project includes update of the control panel and related electrical system at the wastewater treatment plant as well as replacement of the existing generator. Contractor has completed preliminary site work.  Generator delivery anticipated in August 2024.

South Pump Station Generator

Project includes replacement of existing diesel generator at the South Pump Station. Contractor has completed preliminary site work.  Generator delivery anticipated in August 2024.

Elevated Storage Tank and Surface Water Plant Recoating

Project includes recoating of elevated storage tank and components of the surface water treatment plant.  Recoating of the elevated storage tank will include the Pecan Grove graphic on both the north and south facing sides. Contracts are under District review.

Old South Drive Culvert and Road Repairs

Project includes removing and replacing a portion of Old South Drive over the culvert connection of Bullhead Bayou.  Project will also include grout filling and stabilization of any erosion discovered during road repair. Agency inspections were held and passed.  Board approved Pay Request No. 3 & Final in the amount of $11,235.00 and accepted the project as complete.

Storm Sewer Outfall Rehabilitation

Project includes repair and/or replacement of many storm sewer outfalls throughout the District based on inspections. Preconstruction meeting was held on February 21, 2024.  Notice to Proceed to be issued on March 18, 2024.

Projects Under Design

South Pump Station Headwall Modification and Redundant Closure Devices

Project includes modification of headwall structure for the South Stormwater pump station to allow for the design and installation of back up closure devices. Design Paid for out of Bond Issue No. 18 and construction to be funded by a future bond issue. Plans have been approved by City of Richmond and will be submitted to Fort Bend County for approval.

North Pump Station Redundant Closure Devices

Project includes design and installation of back up closure devices at the North Pump Station. Design Paid for out of Bond Issue No. 18 and construction to be funded by a future bond issue. Plans have been approved by City of Richmond and will be submitted to Fort Bend County for approval.

Programming Updates for the Surface Water Treatment Plant

Project includes upgrading the automation and computer components of the plant, including all necessary programming. Engineer reported that design is nearly complete and Board authorized Engineer to advertise for construction with bids expected to be presented at a future meeting.

Belt Press Upgrades at Surface Water Treatment Plant

Project includes upgrading the belt press at the surface water treatment plant to allow for consistent operation and reduce the overall run time of the process. Plans have been reviewed by agencies and will be submitted for approval in March 2024.  Board authorized Engineer to advertise project for construction bids.

Arc Flash Study – Phase Two

Project includes studying electrical control panels for District facilities to ensure compliance with updated regulations. Contractor is nearing completion of the study and expects to finalize in 1st Quarter of 2024.

Waterline Rehabilitation – Phase Two

Project includes replacement of aging waterline infrastructure within Plantation, Section One with additional location of Mayweather Lane between Plantation Drive and Morton League Road. Project to be paid out of bond funds. Topographic survey is complete and design has commenced.

Additional Engineering Items

Fort Bend County Flood Monitoring Cameras

Fort Bend County accepted all comments from MUD attorney and agreement has been finalized.

District Wide Slab Elevation Survey

Engineer reported that the surveyor has started survey operations to obtain the slab elevations for every residential structure inside the levee.  Surveyor is approximately 50% complete.

Land Grant Court

Fort Bend County has begun reconstruction of Land Grant Court.

Brandt Road Improvements

District and County will start coordinating on relocation of entrance to Surface Water Treatment Plant off of the newly constructed Brandt Road.  Brandt Road is expected to open to the public in 3rd Quarter 2024.

 

 


Engineering Updates – Archive