Construction Projects

Proposed Drainage Project Aerial Image

Construction Updates – November 2016

Plantation 7
  • Expected Construction: December 5, 2016 – April 1, 2017
  • Critical Dates:
    • All work from December 5 to January 5 shall be limited to the golf course.
    • Work within residential property or public Right-of-Way shall not be performed until the first week in January.
  • General Layouts of Project
Grove 4 & 5 and Plantation 4 & 5
  • Construction Bid: July 16, 2015
  • General Layouts of Project
  • Construction: September 15, 2015 – November 26, 2016
    • Critical Dates:
      • The contractor has exceeded the contracted completion date. Current estimates for final completion of the project is February 2017.

Construction Updates – September 2016

Grove 4 & 5 and Plantation 4 & 5
  • Construction Bid: July 16, 2015
  • General Layouts of Project
  • Construction: September 15, 2015 – November 26, 2016
    • Critical Dates:
      • Boring between homes is complete. Roadways will be demolished for installation of new piping over the next few weeks, but will be finished prior to Thanksgiving. Proper traffic control plans will be implemented during this work.
      • Construction of the detention ponds will last through the remaining of the completion time.
      • Proper traffic control for Plantation Drive will be implemented, and construction work will be coordinated around school drop-off/pick up times when possible.
Plantation 7
  • Construction Bid: August 30, 2016
  • Expected Construction: December 1, 2016 – April 1, 2017
  • General Layouts of Project

Construction Updates – April 2016

Grove 4 & 5 and Plantation 4 & 5
  • Construction Bid: July 16, 2015
  • General Layouts of Project
  • Construction: September 15, 2015 – November 26, 2016
    • Critical Dates:
      • Grove 4 & 5 construction will be the main focus up to April 2016
      • Boring between homes is near completion, with one remaining. Roadways will be demolished for installation of new piping. Proper traffic control plans will be implemented during this work.
      • The Contractor will move most heavy equipment and work to Plantation 4 & 5 at the end of April. Construction of the detention pond outside of the levee system will last through the remaining of the completion time.
      • Work will continue on Grove 4 & 5, but not the major construction activity currently in place.
      • Proper traffic control for Plantation Drive will be implemented, and construction work will be coordinated around school drop-off/pick up times when possible.
Plantation 7
  • Expected Construction Bid: July 16, 2016
  • Expected Construction: September 20, 2016 – January 18, 2017
    • Schedule is tentative because completion of land acquisition does not have hard completion date.