Plantation 7 – Plantation Work

Construction activity related to the Plantation 7 Drainage Improvements Project on the property of the golf course has completed. All work activities on the golf course are now being conducted by the golf course ownership and not under the guidance of the MUD.

The MUD continues construction for the project along Plantation Drive. The work consists of installing the underground storm pipe along the south side of Plantation Drive towards Quarterpath Drive. It is estimated the work will continue through the middle of June, and is dependent on weather conditions. There will be lane closures along in the work area as the contractor progresses. Traffic control plans have been approved by Fort Bend County and will be implemented for the safety of the contractor and residents of the District. We appreciate your patience as we continue to improve the drainage infrastructure in Pecan Grove MUD.